At the end of last year, the expansion of the geothermal energy installation was started. Hoogweg wants to drill 5 wells: 2 production wells and 3 injection wells. The drilling process was completed by mid-May 2022. The next step is testing the production of heat, this is the phase in which we learn more about the energy (hot water) that we are going to produce. The installation will also be further completed, these are the activities that are carried out above ground.